AKARI HOANG NAM FINISHED CONCRETE POURING ON FLOOR 1, F3 TOWER

26/10/2022

On the evening of October 25, the Akari Hoang Nam construction crew poured a volume of 600 m3 of concrete onto the first floor of tower F3 (AK10).

According to the schedule, the batch of concrete for the first floor of the F3 skyscraper began on October 25 in the evening and was finished on October 26 in the morning. Despite the fact that construction of the tunnel took place during the challenging rainy season, the crew’s intense attention and perseverance allowed for the works to be completed successfully.

Akari City, often known as ‘the Light City,’ is a sizable undertaking by Nam Long Group, in collaboration with its two Japanese partners, Hankyu Hanshin and Nishi Nippon Railroad. As a General Contractor on this project, Ricons is involved in structuring, finishing and installing M&E for the tunnel, body and technical infrastructure, and internal landscape.

The project’s size includes 4 towers, each with 30 floors with 1 basement and 1.690 apartments, spreading across a total floor space of 203,000m2.

OTHER NEWS

thumb

RICONS HOSTS TOPPING-OUT CEREMONY FOR SKYGATE OFFICE BUILDING PROJECT.

09/01/2023

Ricons successfully held the Skygate Office Building project’s topping-out ceremony on January 9, 2023. The project, developed...

thumb

RICONS HOLDS BASEMENT TOPPING-OUT CEREMONY FOR MIXED-USE AREA OF AKARI HOANG NAM LOT F.

30/12/2022

On the morning of December 30, Ricons held a basement topping-out ceremony for Akari Hoang Nam Lot F’s mixed-use...

thumb

[PROJECT UPDATE] RICONS HOLDS COMPLETION CEREMONY FOR T1 TOWER’S ROOF STRUCTURE.

23/12/2022

On the afternoon of December 22, 2022, The Nexus project steering committee held a ceremony to mark the completion of...