UPDATE ON THE PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PASSENGER TERMINAL PROJECT

27/12/2023

Some updates on the Long Thanh International Airport Passenger Terminal project as of December 25, 2023:

  • Over 400 pieces of equipment have been mobilized for construction activities on-site.
  • Excavation work for the underground sections has reached 77%, with a total volume of excavated soil reaching 274,190/356,100 m3.
  • Pile cutting work has reached 62%, with a total of 967/1560 piles cut.
  • Concrete pouring for foundation slabs has reached 56%, with a total of 873/1560 slabs poured.
  • Construction of foundation platforms (reinforcement, formwork, concrete pouring) has reached 10%, with a total of 108/1085 platforms having concrete poured.

With a dedicated work ethic and a sense of urgency on the construction site, the Ricons command team, along with the Vietur consortium, are closely monitoring the progress day and night, ensuring safety and quality in the construction of this large-scale project.

OTHER NEWS

thumb

RICONS OFFICIALLY COMMENCED CONSTRUCTION OF GIANG VO COMPLEX

11/06/2025

Welcoming a vibrant June, on the morning of June 11, 2025, Ricons officially commenced construction of Giang Vo Complex...

thumb

RICONS RESPONDED TO THE ACTION MONTH FOR OCCUPATIONAL SAFETY AND HEALTH 2025

09/06/2025

In May 2025, in response to the Action Month for Occupational Safety and Health (OSH), the Ricons Safety Department launched...

thumb

CENTRAL PARK RESIDENCES – ECO CENTRAL PARK VINH ACCELERATES COMPLETION, ENTERING FINAL STAGE

29/05/2025

After more than a year of intensive construction, Central Park Residences project – located within the eco-urban development...