UPDATE ON THE PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PASSENGER TERMINAL PROJECT

27/12/2023

Some updates on the Long Thanh International Airport Passenger Terminal project as of December 25, 2023:

  • Over 400 pieces of equipment have been mobilized for construction activities on-site.
  • Excavation work for the underground sections has reached 77%, with a total volume of excavated soil reaching 274,190/356,100 m3.
  • Pile cutting work has reached 62%, with a total of 967/1560 piles cut.
  • Concrete pouring for foundation slabs has reached 56%, with a total of 873/1560 slabs poured.
  • Construction of foundation platforms (reinforcement, formwork, concrete pouring) has reached 10%, with a total of 108/1085 platforms having concrete poured.

With a dedicated work ethic and a sense of urgency on the construction site, the Ricons command team, along with the Vietur consortium, are closely monitoring the progress day and night, ensuring safety and quality in the construction of this large-scale project.

OTHER NEWS

thumb

RICONS COMPLETED POWER CONNECTION FOR T3 PASSENGER TERMINAL AT TAN SON NHAT INTERNATIONAL AIRPORT

22/11/2024

In the spirit of urgency and racing against time, on November 19, 2024, T3 Tan Son Nhat project management board,...

thumb

RICONS OFFICIALLY WON THE BID FOR IMPERIA SMART CITY PROJECT – TOWERS V11, V12

21/11/2024

Recently, Ricons marked another milestone by officially winning the bid to execute Imperia Smart City project – Towers V11...

thumb

THE COMMENCEMENT CEREMONY OF LUMI HANOI PROJECT BY RICONS, NEWTECONS, AND SOL E&C IN PARTNERSHIP WITH CAPITALAND DEVELOPMENT

12/11/2024

On the morning of November 11, 2024, Ricons, Newtecons, and SOL E&C held the commencement ceremony for Lumi Hanoi...