UPDATE ON THE PROGRESS OF LONG THANH INTERNATIONAL AIRPORT PASSENGER TERMINAL PROJECT

27/12/2023

Some updates on the Long Thanh International Airport Passenger Terminal project as of December 25, 2023:

  • Over 400 pieces of equipment have been mobilized for construction activities on-site.
  • Excavation work for the underground sections has reached 77%, with a total volume of excavated soil reaching 274,190/356,100 m3.
  • Pile cutting work has reached 62%, with a total of 967/1560 piles cut.
  • Concrete pouring for foundation slabs has reached 56%, with a total of 873/1560 slabs poured.
  • Construction of foundation platforms (reinforcement, formwork, concrete pouring) has reached 10%, with a total of 108/1085 platforms having concrete poured.

With a dedicated work ethic and a sense of urgency on the construction site, the Ricons command team, along with the Vietur consortium, are closely monitoring the progress day and night, ensuring safety and quality in the construction of this large-scale project.

OTHER NEWS

thumb

RICONS UPDATES CONSTRUCTION PROGRESS OF ECO HH1 PROJECT – LONG AN | APRIL 2026

09/04/2026

In April 2026, Eco HH1 Project – Subzone 6, developed by Ecopark Group in Long An, was actively executed by...

thumb

RICONS COMMENCES CONSTRUCTION OF MASTERI GRAND COAST APARTMENT PROJECT – HUNG YEN

27/03/2026

On March 27, 2026, Ricons , in collaboration with Newtecons and SOL E&C, officially commenced construction of the ...

thumb

RICONS UPDATES PROGRESS OF SUN FELIZA SUITES PROJECT: SUCCESSFULLY COMPLETING THE CONCRETE POURING OF 5 PIT FOUNDATION CAPS WITH A TOTAL VOLUME OF 7,800 m³

19/03/2026

Over five consecutive days and nights, from March 14 to 18, 2026, Ricons, in collaboration with SOL E&C, successfully completed...