THE GIO RIVERSIDE PROJECT UPDATE – SEPTEMBER 2025

10/09/2025

On September 9, 2025, The Gio Riverside project marked an important milestone with the successful completion of the first-floor beam and slab concrete pour covering an area of 1,200 m².

This event marked the completion of the first-floor beam and slab structure – one of the key milestones of the project. In the coming period, the site will continue with the excavation of basements B2 and B3.

Despite frequent heavy rainfall, the site management team has made great efforts to overcome difficulties, ensuring Safety – Quality – Schedule for the project. This is a clear testament to the perseverance and determination of the Ricons team.

Located at the confluence of the Dong Nai River and Ngoc River, The Gio Riverside enjoys a prime location with expansive views, while offering convenient connections to major arterial roads, creating outstanding advantages for both commerce and residence.

The project is expected to become a modern green living icon in Binh Duong, bringing residents a lifestyle close to nature along with full urban amenities.

PROJECT OVERVIEW

  • Project name: The Gio Riverside
  • Developer: An Gia Group

Project scale:

  • 02 L-shaped blocks: Gio Dong Tower (Block A) and Gio Nam Tower (Block B)
  • 40 above-ground floors, 03 basements
  • 2,905 apartments, 76 shophouses
  • Total gross floor area: ~297,000 m²
  • Residential building density: 30.73%

As the General Contractor, Ricons continues to affirm the reputation and capacity, committing to work alongside the Developer to deliver a project that meets expectations in terms of quality, schedule, and safety, creating a development worthy of being an ideal place to live and prosper for the future community.

 

OTHER NEWS

thumb

NARRA RESIDENCES PROJECT SUCCESSFULLY COMPLETES TRANSFER SLAB CONCRETE POUR AT TOWER N1

01/06/2026

Last week, at Narra Residences project, Ricons successfully completed the concrete pour for the Level 3 transfer slab...

thumb

ELYSIAN PROJECT HONORED WITH CERTIFICATE FOR ACHIEVING 2 MILLION SAFE MAN-HOURS

26/05/2026

In May 2026, Elysian project was honored to receive a certificate from Gamuda Land for achieving...

thumb

RICONS SPEEDS UP CONSTRUCTION AT TT AVIO PROJECT, TOWER A APPROACHES TOPPING-OUT MILESTONE | 5/2026

23/05/2026

Join Ricons as we update the construction progress of TT Avio in May 2026. Regarding structural works, the project...