PROJECT PROGRESS UPDATE: THE MATRIX ONE – PHASE 2 | HANOI – MARCH 2026

10/03/2026

Entering March 2026, projects implemented by Ricons across the country are being accelerated with a strong sense of urgency and focus, ensuring Safety – Quality – Progress in accordance with the planned schedule.

At the HH1 high-rise mixed-use building project, part of the Golden Palace A Entertainment Park, School and Residential – Commercial – Service Complex (The Matrix One – Phase 2) in Hanoi, construction activities are being carried out simultaneously across multiple work packages.

Construction progress update – The Matrix One Phase 2:

  • HH1-1 Tower: Structural works have reached Level 29
  • HH1-2 Tower: Structural works have reached Level 24
  • Finishing works: Currently progressing up to Level 22

The Site Management Board is focusing on resources and accelerating construction progress while strengthening quality control across each work package to ensure the project fully meets technical standards and maintains strict safety management throughout the construction process.

Project overview

Project name: HH1 High-rise Mixed-use Building – Golden Palace A Entertainment Park, School and Residential – Commercial – Service Complex (The Matrix One – Phase 2)
Developer: Mai Linh Investment Joint Stock Company
Location: Tu Liem Ward, Hanoi

  • HH1-1 Tower: 3 basement levels and 44 above-ground floors
  • HH1-2 Tower: 3 basement levels and 37 above-ground floors
  • Total apartments: 990 units

According to the project schedule, the topping-out milestone is expected in June 2026.

OTHER NEWS

thumb

RICONS UPDATES CONSTRUCTION PROGRESS OF ECO HH1 PROJECT – LONG AN | APRIL 2026

09/04/2026

In April 2026, Eco HH1 Project – Subzone 6, developed by Ecopark Group in Long An, was actively executed by...

thumb

RICONS COMMENCES CONSTRUCTION OF MASTERI GRAND COAST APARTMENT PROJECT – HUNG YEN

27/03/2026

On March 27, 2026, Ricons , in collaboration with Newtecons and SOL E&C, officially commenced construction of the ...

thumb

RICONS UPDATES PROGRESS OF SUN FELIZA SUITES PROJECT: SUCCESSFULLY COMPLETING THE CONCRETE POURING OF 5 PIT FOUNDATION CAPS WITH A TOTAL VOLUME OF 7,800 m³

19/03/2026

Over five consecutive days and nights, from March 14 to 18, 2026, Ricons, in collaboration with SOL E&C, successfully completed...