T3 Passenger Terminal project at Tan Son Nhat International Airport is entering the final sprint towards completion.
On the morning of February 11, 2025, Mr. Tran Quang Quan – General Director and Mr. Nguyen Thanh Tam – Operations Director, conducted an on-site inspection, urging progress and engaging with the project team. Accompanying the boards of directors were representatives from the Human Resources Department, Trade Union Executive Committee and other departments. During the visit, the boards of directors and department representatives extended words of encouragement to the project team and shared insights into Ricons’ future development direction.
Commenced in August 2023, T3 passenger terminal project has now reached approximately 83% completion. As of February 2025, the primary structure, including the roof, basement, elevated roadway and departure/arrival halls, has been finalized. The entire power system—from RMU substation to medium-voltage panels, transformers, and MSB cabinets at the UC, PTB, and PNA areas—has been successfully powered up. Technical systems, equipment installation, and interior finishing are being expedited to ensure timely completion.
PROJECT INFORMATION:
✔ Project Name: T3 Passenger Terminal at Tan Son Nhat International Airport
✔ Investor: Airports Corporation of Vietnam (ACV)
✔ Total Area: 112,500 m²
✔ Scale: 1 basement, 4 above-ground floors
✔ Capacity: 20 million passengers per year
T3 project team remains committed to accelerating efforts in the final phase, ensuring all commitments to the investor are met.
T3 terminal is scheduled for completion and official operation on April 30, 2025, marking the 50th anniversary of the reunification of Vietnam.