THE GIO RIVERSIDE PROJECT CONQUERS A KEY CONCRETE POUR AT ZONE 2

10/07/2025

On the evening of July 8, 2025, the management team of The Gio Riverside project successfully carried out the concrete pouring for the Zone 2, 1st floor slab. With a total volume of nearly 500 m³ of concrete covering an area of over 1,100 m², this pour marks a significant milestone in the basement construction phase of the project.

Although the work coincided with the rainy season—bringing considerable challenges in terms of weather and site conditions—the project management team demonstrated exceptional focus, proactive adaptability, and strong determination, ensuring the pour was completed safely, to technical standards, and on schedule.

PROJECT OVERVIEW:

  • Project name: The Gio Riverside
  • Developer: An Gia Group
  • – Project scale:
  • ✓ 2 L-shaped towers
  • ✓ 40 above-ground floors, 3 basement levels
  • ✓ 2,905 apartments, 76 shophouses
  • ✓ Total construction floor area: ~297,000 m²
  • ✓ Residential building coverage ratio: 30.73%

In addition to the residential area, the project also features a school facility with a construction floor area of 14,484 m² and a building coverage ratio of just 9.43%, offering a complete, convenient, and ideal living environment for its residents.

Congratulations to The Gió Riverside project management team for conquering this important concrete pouring milestone. As the General Contractor, Ricons will continue to progress confidently in the next stages of the project, ensuring safety, quality, and timely delivery in line with our commitments to the Developer.

OTHER NEWS

thumb

RICONS WELCOMES NEARLY 80 NEW EMPLOYEES – BUILDING CONNECTIONS FROM DAY ONE

20/08/2026

On the morning of August 20, 2026, nearly 80 new employees across Southern and Northern Vietnam participated in the ...

thumb

RICONS UPDATES CONSTRUCTION PROGRESS AT SUN FELIZA SUITES – AUG 2026

07/08/2026

Take a look at the latest construction images from the Sun Feliza Suites project with Ricons. At the project,...

thumb

RICONS TOPS OUT LOW-RISE RESIDENTIAL DEVELOPMENT AT GOLDEN PALACE A

03/08/2026

On the morning of August 2, 2026, Ricons held the topping-out ceremony for the low-rise residential development under the Golden...