RICONS UPDATES CONSTRUCTION PROGRESS OF ECO HH1 PROJECT – LONG AN | APRIL 2026

09/04/2026

In April 2026, Eco HH1 Project – Subzone 6, developed by Ecopark Group in Long An, was actively executed by Ricons in line with the planned schedule. Acting as the Design & Build General Contractor, Ricons mobilized resources and implemented synchronized construction measures to ensure the project’s key objectives of Safety – Quality – Progress.

Construction progress update:

Two residential towers: Structural works reached Level 3

Underground parking area: Over 70% of the structural works has been completed

Upcoming implementation plan:

– Continue focusing on structural works across all zones

– In Q2 2026, the project is scheduled to commence the construction of the mock-up floor

During the execution phase, the project has encountered several challenges, including underground works carried out during the prolonged rainy season, as well as general market fluctuations. However, the Site Management Board has proactively coordinated resources and optimized construction methodologies to maintain the overall project schedule.

With a proactive and determined approach, Eco HH1 Project continues to maintain stable construction momentum, gearing up for key milestones in Q2 2026.

OTHER NEWS

thumb

250 STUDENTS FROM HANOI UNIVERSITY OF CIVIL ENGINEERING VISIT RICONS AND ECOSYSTEM PROJECTS

19/05/2026

As part of its university partnership programs, Ricons, together with other companies in the Ecosystem, recently organized a site visit...

thumb

THE “HEAT” AT ATERA CENTRAL IN THE SUMMER DAYS OF MAY 2026

18/05/2026

In May 2026, Atera Central project continued to accelerate construction activities, closely following the implementation schedule and the...

thumb

PARK VILLAGE SOUTHGATE: RICONS SPEEDS UP CONSTRUCTION OF 96 VILLAS | 5/2026

15/05/2026

Join Ricons as we visit the construction site of the 96-Villa Park Village Project , part of the ...