RICONS OFFICIALLY TOPS OUT TOWER O OF K8HH1 HIGH-RISE MIXED-USE RESIDENTIAL PROJECT

08/05/2026

On May 7, 2026, Ricons, in collaboration with the Developer, THT Development Co., Ltd., and the General Contractor, Daewoo E&C Vina, successfully held the topping-out ceremony for Tower O, the office tower of the K8HH1 High-Rise Mixed-Use Residential Project.

Located at Lot K8 in the central area of Starlake Urban Township, Xuan Dinh Ward, Hanoi, the project is strategically positioned in one of the capital’s most dynamic development areas. The development comprises three towers and two shared basement levels, including:

Two 26-storey residential towers, providing 284 modern apartments.
One 20-storey office tower, designed to meet the demand for high-quality working spaces.

Commenced on March 20, 2025, the project has now reached the topping-out milestone for Tower O after nearly 14 months of construction, in line with the planned schedule.

As a project delivered in collaboration with Daewoo E&C Vina, one of South Korea’s leading general contractors, K8HH1 High-Rise Mixed-Use Residential Project continues to affirm Ricons’ construction capabilities in projects with stringent requirements for technical execution, quality, and progress. The project also stands as a testament to the effective cooperation between Vietnamese and Korean enterprises in the construction sector.

Throughout the construction process, Ricons has focused its resources, maintained strict construction control, and ensured the core criteria of Safety – Quality – Progress.

Entering the finishing phase, the Site Management Board will continue to make every effort to meet the project’s rigorous requirements, working towards the goal of handing over the project in line with its commitments.

Congratulations to the entire Site Management Board of K8HH1 High-Rise Mixed-Use Residential Project on achieving this significant milestone.

OTHER NEWS

thumb

NARRA RESIDENCES PROJECT SUCCESSFULLY COMPLETES TRANSFER SLAB CONCRETE POUR AT TOWER N1

01/06/2026

Last week, at Narra Residences project, Ricons successfully completed the concrete pour for the Level 3 transfer slab...

thumb

ELYSIAN PROJECT HONORED WITH CERTIFICATE FOR ACHIEVING 2 MILLION SAFE MAN-HOURS

26/05/2026

In May 2026, Elysian project was honored to receive a certificate from Gamuda Land for achieving...

thumb

RICONS SPEEDS UP CONSTRUCTION AT TT AVIO PROJECT, TOWER A APPROACHES TOPPING-OUT MILESTONE | 5/2026

23/05/2026

Join Ricons as we update the construction progress of TT Avio in May 2026. Regarding structural works, the project...