RICONS SPEEDS UP CONSTRUCTION AT TT AVIO PROJECT, TOWER A APPROACHES TOPPING-OUT MILESTONE | 5/2026

23/05/2026

Join Ricons as we update the construction progress of TT Avio in May 2026.

Regarding structural works, the project is currently carrying out construction of the 30th floor structure of Tower A and the basement structure of Tower B. Finishing works are also being accelerated, with masonry works completed up to the 21st floor, while various interior finishing items within the apartments are being implemented in line with the project schedule.

Commenced on August 1, 2024, TT Avio has continued to meet stringent requirements for safety, quality, and progress, earning positive recognition from the Developer. As planned, Tower A is expected to reach its topping-out milestone in June 2026, marking an important achievement in the project’s construction journey.

PROJECT INFORMATION

– Project name: TT Avio
– Developer: Joint Venture Investment and Development Entity Comprising Japan’s Cosmos Initia, TT Capital, and Koterasu Partner
– Location: Frontage of DT743C Road, Di An Ward, Ho Chi Minh City
– Scale: Two towers, A and B, with 30 and 37 floors respectively; two shared basement levels
– Total land area: 1.6 hectares
– Contract package: Design & Build General Contractor

TT Avio is developed with apartments ranging from 40 to 67 square meters, featuring diverse design styles and aiming to deliver a high-standard living environment aligned with Japanese criteria. As the Design & Build General Contractor, Ricons continues to focus its resources and maintain strict control over each construction item, ensuring the project is delivered safely, with quality, and in accordance with the committed schedule.

OTHER NEWS

thumb

RICONS UPDATES CONSTRUCTION PROGRESS AT SUN FELIZA SUITES – AUG 2026

07/08/2026

Take a look at the latest construction images from the Sun Feliza Suites project with Ricons. At the project,...

thumb

RICONS TOPS OUT LOW-RISE RESIDENTIAL DEVELOPMENT AT GOLDEN PALACE A

03/08/2026

On the morning of August 2, 2026, Ricons held the topping-out ceremony for the low-rise residential development under the Golden...

thumb

RICONS TOPS OUT G5–G6 TOWERS AT THE SOLA PARK

30/07/2026

On the morning of July 30, 2026, Ricons held the topping-out ceremony for the G5 and G6 towers at The...