At The Sola Park project, structural works are being implemented in a synchronized manner, closely following the planned schedule.
Currently, the tower block has completed 100% of the structural works from the foundation slab to the 2nd floor. The site management team and construction crew are continuing with the column–wall structures for floors 2–3 and the 3rd-floor slab.
In the coming period, the project’s key target is to close the basement roof by the end of July 2025 and complete the transfer floor structure at the 6th floor in September 2025.
With a proactive and determined approach from the site management team, The Sola Park project is maintaining a steady construction pace, ready for the upcoming key milestones.
![]()